You are the project manager for the TTR project. You are in the process of gathering information for risk identification

Posted: Fri Aug 26, 2022 9:54 am
by answerhappygod
You are the project manager for the TTR project. You are in the process of gathering information for risk identification. You ask experts to participate in the process through their emails for maintaining anonymity. You collect the responses, summarize them, and are then re-circulated to the experts for further comment. Which of the following techniques are you using for risk identification?

A. SWOT analysis
B. Delphi
C. Expert judgment
D. Brainstorming