You are the project manager for the TTR project. You are in the process of gathering information for risk identification
Posted: Fri Aug 26, 2022 9:54 am
You are the project manager for the TTR project. You are in the process of gathering information for risk identification. You ask experts to participate in the process through their emails for maintaining anonymity. You collect the responses, summarize them, and are then re-circulated to the experts for further comment. Which of the following techniques are you using for risk identification?
A. SWOT analysis
B. Delphi
C. Expert judgment
D. Brainstorming
A. SWOT analysis
B. Delphi
C. Expert judgment
D. Brainstorming