The phase 3 of the Risk Management Framework (RMF) process is known as mitigation planning. Which of the following proce

Posted: Thu Aug 18, 2022 8:14 am
by answerhappygod
The phase 3 of the Risk Management Framework (RMF) process is known as mitigation planning.
Which of the following processes take place in phase 3?
Each correct answer represents a complete solution. Choose all that apply.

A. Identify threats, vulnerabilities, and controls that will be evaluated.
B. Document and implement a mitigation plan.
C. Agree on a strategy to mitigate risks.
D. Evaluate mitigation progress and plan next assessment.