You are the business analyst for your organization. As part of the requirements prioritization you have given each key s
Posted: Thu Aug 18, 2022 8:11 am
You are the business analyst for your organization. As part of the requirements prioritization you have given each key stakeholder $10,000 in play money to distribute among the identified requirements. Each stakeholder can assign their play money to any of the requirements, but the requirements will be prioritized based on the value of the play money assigned to each requirement.
What type of requirements prioritization is happening in this scenario?
A. Resource leveling
B. Confirmation management
C. Utility function
D. Voting
What type of requirements prioritization is happening in this scenario?
A. Resource leveling
B. Confirmation management
C. Utility function
D. Voting