Assume that the following test cases have been executed at the end of the first week of test execution: TC-001, TC-002 and TC-007. All these tests are passes.What is the MINIMUM number of the remaining test cases that must be successfully executed to fulfill the EX1 exit criteria?Number of correct responses: 1 -K3 2 credits -
Assume That The 1
Assume That The 1 (35.27 KiB) Viewed 91 times
A. 4
B. 5
C. 6
D. 7