You are the project manager of the NNH Project. In this project you have created a contingency response that the schedule performance index should be less than 0.93. TheNHH Project has a budget at completion of $945,000 and is 45 percent complete though the project should be 49 percent complete. The project has spent $455,897 to reach the 45 percent complete milestone.What is the project's schedule performance index?

A. 1.06
B. 0.92
C. -$37,800
D. 0.93