You are the project manager of GHT project. Your hardware vendor left you a voicemail saying that the delivery of the eq
Posted: Tue Aug 16, 2022 6:10 am
You are the project manager of GHT project. Your hardware vendor left you a voicemail saying that the delivery of the equipment you have ordered would not arrive on time. You identified a risk response strategy for this risk and have arranged for a local company to lease you the needed equipment until yours arrives.This is an example of which risk response strategy?
A. Avoid
B. Transfer
C. Acceptance
D. Mitigate
A. Avoid
B. Transfer
C. Acceptance
D. Mitigate