You are the project manager of GHT project. Your hardware vendor left you a voicemail saying that the delivery of the eq

Posted: Tue Aug 16, 2022 6:10 am
by answerhappygod
You are the project manager of GHT project. Your hardware vendor left you a voicemail saying that the delivery of the equipment you have ordered would not arrive on time. You identified a risk response strategy for this risk and have arranged for a local company to lease you the needed equipment until yours arrives.This is an example of which risk response strategy?

A. Avoid
B. Transfer
C. Acceptance
D. Mitigate