You work as a project manager for BlueWell Inc. You have declined a proposed change request because of the risk associat
Posted: Tue Aug 16, 2022 6:10 am
You work as a project manager for BlueWell Inc. You have declined a proposed change request because of the risk associated with the proposed change request.Where should the declined change request be documented and stored?
A. Change request log
B. Project archives
C. Lessons learned
D. Project document updates
A. Change request log
B. Project archives
C. Lessons learned
D. Project document updates