You are the project manager of HGT project. You have identified project risks and applied appropriate response for its mitigation. You noticed a risk generated as a result of applying response. What this resulting risk is known as?
A. Pure risk
B. Secondary risk
C. Response risk
D. High risk
A. Pure risk
B. Secondary risk
C. Response risk
D. High risk