You are the project manager of your project. You have to analyze various project risks. You have opted for quantitative analysis instead of qualitative risk analysis.What is the MOST significant drawback of using quantitative analysis over qualitative risk analysis?
A. lower objectivity
B. higher cost
C. higher reliance on skilled personnel
D. lower management buy-in