You are the project manager of GHT project. Your hardware vendor left you a voicemail saying that the delivery of the equipment you have ordered would not arrive on time. She wanted to give you a heads-up and asked that you return the call. Which of the following statements is TRUE?

A. This is a residual risk.
B. This is a trigger.
C. This is a contingency plan.
D. This is a secondary risk.