Harry is the project manager of HDW project. He has identified a risk that could injure project team members. He does not want to accept any risk where someone could become injured on this project so he hires a professional vendor to complete this portion of the project work. What type of risk response is Harry implementing?

A. Transference
B. Mitigation
C. Acceptance
D. Avoidance