At the seventh Sprint Review, the stakeholders are disappointed and angry.

Posted: Wed Aug 10, 2022 6:25 pm
by answerhappygod
At the seventh Sprint Review, the stakeholders are disappointed and angry. When asked about it, they say the product being built will not meet their needs and will cost more than they anticipated spending. What factors likely led to this? willing to spend. What factors may have led to this?

At The Seventh Sprint Review The Stakeholders Seem Disappointed
At The Seventh Sprint Review The Stakeholders Seem Disappointed (101.01 KiB) Viewed 151 times

(choose the best three answers)


A. The stakeholders were not allowed to enter the development area, or be present at the Daily Scrum.

B. The Scrum Master has not ensure transparency.

C. The Product Owner has not been interacting frequently with the stakeholders and kept them aware of the progress of the project.

D. The stakeholders have not been using the Sprint Reviews to actively engage, and inspect and evaluate progress.

E. Changes to the project plan were not adequately documented and shared. The change request procedure was not diligently followed.

F. The Project Management Office (PMO) and its project managers have not been adequately engaged, causing the project plan to become inaccurate.