You work as a project manager for TYU project. You are planning for risk mitigation. You need to identify the risks that
Posted: Mon Aug 01, 2022 9:35 am
You work as a project manager for TYU project. You are planning for risk mitigation. You need to identify the risks that will need a more in-depth analysis. Which of the following activities will help you in this?
A. Qualitative analysis
B. Quantitative analysis
C. Risk identification
D. Estimate activity duration
A. Qualitative analysis
B. Quantitative analysis
C. Risk identification
D. Estimate activity duration