You work as a project manager for TYU project. You are planning for risk mitigation. You need to identify the risks that

Posted: Mon Aug 01, 2022 9:35 am
by answerhappygod
You work as a project manager for TYU project. You are planning for risk mitigation. You need to identify the risks that will need a more in-depth analysis. Which of the following activities will help you in this?

A. Qualitative analysis
B. Quantitative analysis
C. Risk identification
D. Estimate activity duration