Page 1 of 1

An organization has a standardized change management plan that all project managers must adhere to. A project manager ha

Posted: Mon Aug 01, 2022 9:35 am
by answerhappygod
An organization has a standardized change management plan that all project managers must adhere to. A project manager has worked with the Change Control
Board in his organization to approve a change to project scope. What should the standardized change management plan require the project manager to do with the approved scope change?

A. Perform risk assessment on the new change.
B. Communicate the change to the vendor.
C. Create a cost estimate for the change.
D. Update the WBS.