Tau Limited uses the economic order quantity (EOQ) model to determine the quantity of raw materials to order. The following details concerning the raw materials are presented to you:
= 480 Quantity of raw materials used per day units = = 250 Number of production days per year days Cost of placing an order = = R60 = Invoicing cost price per unit R10,50 Annual holding/carrying costs = R3,60 per unit The number of orders to be placed in a year amount to Select one: O A. 30 orders B. 60 orders C. 88 orders D. 20 orders
= 480 Quantity of raw materials used per day units = = 250 Number of production days per year days Cost of placing an order = = R60 = Invoicing cost price per unit R10,50 Annual holding/carrying costs = R3,60 per unit The number of orders to be placed in a year amount to Select one: O A. 30 orders B. 60 orders C. 88 orders D. 20 orders