Refer to the exhibit. After a failover occurs, which two actions must be performed on Switch-B to manually preempt the operational primary role back to Switch-A?
(Choose two.)
Refer To The Ex 1
Refer To The Ex 1 (75.98 KiB) Viewed 51 times
A. Configure the local vPC role priority to have a lower value than Switch-A.
B. Configure the local vPC role priority to have a higher value than Switch-A.
C. Disable and then re-enable the vPC peer-keepalive link.
D. Configure the local vPC role priority to have the same value as Switch-A.
E. Disable and then re-enable the vPC peer link.