Page 1 of 1

4 A project consists of (ELEVEN) activities, A to K. The duration (in days), and the activities preceding each of them s

Posted: Thu Jul 14, 2022 3:00 pm
by answerhappygod
4 A Project Consists Of Eleven Activities A To K The Duration In Days And The Activities Preceding Each Of Them S 1
4 A Project Consists Of Eleven Activities A To K The Duration In Days And The Activities Preceding Each Of Them S 1 (75.8 KiB) Viewed 45 times
4 A project consists of (ELEVEN) activities, A to K. The duration (in days), and the activities preceding each of them shown in Table Q4. i. Construct a PERT network diagram for the project. Assuming that the slack time for each activity is 1 (ONE) day, state the early start, late start, early finish and late finish in the diagram. ( 9 marks) ii. Find the critical path in the network diagram