Your are managing your first construction project for Soprano Construction Corp, The project is at about 30-percent comp
Posted: Thu Jul 14, 2022 2:57 pm
Your are managing your first construction project for Soprano Construction Corp, The project is at about 30-percent completion and when your are doing your monthly budget review you note that the budget for one of the trades was under estimated and will go way over budget. What should you do? All of the above What until the end of the project to see if the other trades make up the difference Develop a plan to resolve the issue and present it to your boss as soon as possible Take a vacation day