Page 1 of 1

QUESTION 1 [40 MARKS] (a) Determine the critical path of the project [10 Marks] (b) Illustrate the Tasks on a Gantt Char

Posted: Thu Jul 14, 2022 2:45 pm
by answerhappygod
Question 1 40 Marks A Determine The Critical Path Of The Project 10 Marks B Illustrate The Tasks On A Gantt Char 1
Question 1 40 Marks A Determine The Critical Path Of The Project 10 Marks B Illustrate The Tasks On A Gantt Char 1 (77.59 KiB) Viewed 36 times
thank you
QUESTION 1 [40 MARKS] (a) Determine the critical path of the project [10 Marks] (b) Illustrate the Tasks on a Gantt Chart. [10 Marks] (c) Calculate the planned duration of the project. [10 Marks] (d) Identify and explain any non-critical tasks and the float (free slack) on each. [10 Marks]