4 A project consists of (E.I.VEN) activities, A to K. The duration (in days), and the activities preceding each of them
Posted: Thu Jul 14, 2022 2:38 pm
4 A project consists of (E.I.VEN) activities, A to K. The duration (in days), and the activities preceding each of them shown in Table Q4. i. Construct a PERT network diagram for the project. Assuming that the slack time for each activity is 1 (ONE) day, state the early start, late start, early finish and late finish in the diagram. (9 marks) ii. Find the critical path in the network diagram