Q1- A- The following table gives activities of durations of construction project work; draw the network for the project
Posted: Tue Apr 26, 2022 3:27 pm
Q1- A- The following table gives activities of durations of construction project work; draw the network for the project and find:- (1) The critical path. (ii) The free float time. (iii) The total float A B с Activity Predecessors Duration (days) - D A 10 E A 16 F D.B 17 G с 18 H с 14 1 F G 9 8 10 8