- • The soil is clay = 3000 lb / bcy • The earth haul road will be well maintained → RR = 80 lb / ton= 4 %. • Assume ave
Posted: Tue Apr 26, 2022 1:23 pm
- • The soil is clay = 3000 lb / bcy • The earth haul road will be well maintained → RR = 80 lb / ton= 4 %. • Assume average load time 0.85 minute. (fixed time) • From load - growth curve, the expected load will be 96 % of heaped capacity. • 50 min. / hr in used.