3. Pavement Overlay From a site investigation, the condition of the existing pavement is as follow: 18 cm 25 cm Laston M
Posted: Tue Apr 26, 2022 1:23 pm
3. Pavement Overlay From a site investigation, the condition of the existing pavement is as follow: 18 cm 25 cm Laston MS-744; a =0,40; Performance: 75% Crushed stone CBR 100%; a=0,14; Performance: 80% Sirtu/Pitrun CBR 70%; a=0,13; Performance: 85% 40 cm Design the required overlay with Component Analysis Method and sketch the pavement layer. Use ITP from question no.2.