Q6. (10 points) Consider the following network. The activity durations (in days) are shown in the nodes, the variance of
Posted: Tue Apr 26, 2022 12:48 pm
Q6. (10 points) Consider the following network. The activity durations (in days) are shown in the nodes, the variance of all activities is 1 day except for activities D, F, and G; their variance is 2 days. a) Identify all paths in the network. Answer: b) Identify the critical path. Answer: c) How long will it take to complete the project? Answer: d) Compute the probability that the project will be completed in 22 days. Answer: