Given the project information in the table below: Task Follows Task(s) Start A A A CD E B Duration (Weeks) Normal Crash
Posted: Tue Apr 26, 2022 12:32 pm
Given the project information in the table below: Task Follows Task(s) Start A A A CD E B Duration (Weeks) Normal Crash 4 3 4 6 4 4 2 B с D E F | | | ئازاد Cost (thousand dollars) Normal Crash $6,000 $7,200 $10,000 $11,500 $18,000 $19,000 $12,000 $14,000 $4,000 $4,750 $2,000 $2.250 1 3 2 (a) Create a Gantt chart for all tasks assuming that all tasks begin as early as possible. (6 marks) (b) Draw a PDM network diagram. (4 iarks) (C) Identify the critical path and determine its duration. (2 marks) (d) Calculate the slope of each activity (in terms of dollars/week). (6 marks) (e) Determine which task(s) you would crash and the total cost and duration for completing the project by One week carlier. (3 marks) One more weck earlier after part (1). (4 marks)