Q5. (10 points) Given the following information for a project, draw the AON (Activity-On-Node) project network in the sp
Posted: Tue Apr 26, 2022 12:31 pm
Q5. (10 points) Given the following information for a project, draw the AON (Activity-On-Node) project network in the space provided below. Activity Immediate Activity Time Processor (days) А B с D E F G H AB B с CD D E.F.G 6 8 5 4 7 3 6 5 Q6. (10 points) Consider the following network. The activity durations (in days) are shown in the nodes, the variance of all activities is 1 day except for activities D, F, and G; their variance is 2 days. a) Identify all paths in the network. Answer: b) Identify the critical path. Answer: c) How long will it take to complete the project? Answer: d) Compute the probability that the project will be completed in 22 days. Answer: