Q1. (10 points) Consider the following project. Activity A B с D E F G H Immediate Activity Time Processor (days) 8 6 AB

Posted: Tue Apr 26, 2022 12:30 pm
by answerhappygod
 1
1 (20.32 KiB) Viewed 43 times
Q1. (10 points) Consider the following project. Activity A B с D E F G H Immediate Activity Time Processor (days) 8 6 AB 4 B 5 C 7 CD 7 D 9 EFG 6 a) Determine the critical path. b) Determine the estimated completion time of the project. c) Determine the slack for activity D. d) Determine the slack for activity F. c) How much can activity F be delayed without delaying the project completion?