Question 4 1 pts Three activities are candidates for crashing on a project network for a large computer installation (al

Posted: Tue Apr 26, 2022 12:30 pm
by answerhappygod
Question 4 1 Pts Three Activities Are Candidates For Crashing On A Project Network For A Large Computer Installation Al 1
Question 4 1 Pts Three Activities Are Candidates For Crashing On A Project Network For A Large Computer Installation Al 1 (53.91 KiB) Viewed 51 times
Question 4 1 pts Three activities are candidates for crashing on a project network for a large computer installation (all are, of course, critical). Activity details are in the following table: Activity Predecessor A Normal Normal Time Cost 7 days $6,000 4 days $1,200 11 days $4,000 Crash Crash time Cost 6 days $6,600 2 days $3,000 9 days $6,000 B A с B a. What activity would you crash first and how much would it cost to reduce the critical path by 1 day? a. $600 b. Assuming no other paths become critical, what action would you take to reduce the critical path one additional day? (activity and cost) b, $900 c. What is the total cost of the 2-day reduction? $ (Select] [