Network Diagram Without Lag Consider the below project network diagram. А B Task 2 Task 6 Task 8 Task 9 5 4 F 4 3 E Task
Posted: Tue Apr 26, 2022 12:28 pm
Network Diagram Without Lag Consider the below project network diagram. А B Task 2 Task 6 Task 8 Task 9 5 4 F 4 3 E Task 1 N Task 4 M Task 7 Task 12 1 H2 3 2. С D Task 3 Task 5 Task 10 P|Task 11 L3 2 G 5 Answer the following questions regarding Early Start, Early Finish, Late Start, Late Finish, and Slack values. Question 1 (3 points) What is the value of "P"? 2
Question 2 (3 points) What is the value of "H"? 6 8 5 9 10 Question 3 (3 points) What is the value of "E"?
What is the value of "E"? 20 19 21 24 15 Question 4 (3 points) Which of the following tasks are on the critical path. Select as many as needed. Task 3 Task 8 Task 9
Task 8 Task 9 Task 1 Task 5 Task 11 Task 2 Task 6 Task 7 Task 12 Task 4 Task 10
Question 2 (3 points) What is the value of "H"? 6 8 5 9 10 Question 3 (3 points) What is the value of "E"?
What is the value of "E"? 20 19 21 24 15 Question 4 (3 points) Which of the following tasks are on the critical path. Select as many as needed. Task 3 Task 8 Task 9
Task 8 Task 9 Task 1 Task 5 Task 11 Task 2 Task 6 Task 7 Task 12 Task 4 Task 10