Acre Pre- Crash Cost Time Uing Adobe a b 2. Given the following project (all times are in days): Normal Normal Crash Act
Posted: Tue Apr 26, 2022 12:14 pm
Acre Pre- Crash Cost Time Uing Adobe a b 2. Given the following project (all times are in days): Normal Normal Crash Activity decessor Time Cost SSO S150 40 200 70 160 ac 20 50 ac 30 b 80 290 d SO 100 ef 60 180 (a) Draw the network and find the critical path, time, and cost for an all-normal level of project activity. (b) Calculate the crash cost-per-day (all activities may be partially crashed) le (c) Find the optimal way of getting an 18-day delivery time. What is the project cost? (d) Find the optimal way of getting a 16-day delivery time. What is the project cost? Calculate the shortest delivery time for the project. What is the cost? c d e f 5 4 7 2 3 8 5 6 3 2 6 1 - 5 4 3 h Pan Pa Edi