As per the below table, create the precedence diagram, find the critical path of the project and calculate the probabili
Posted: Mon Apr 25, 2022 9:22 am
As per the below table, create the precedence diagram, find the critical path of the project and calculate the probability it is completed within 35 days or less. Activity Predecessor a b m A 5 13 B 2 10 E ao 009 с A.B 3 13 D A,B 1 13 E D 8 12 10 i i F CE 9 15 12