Page 1 of 1

1. a) b)

Posted: Tue Jul 12, 2022 8:05 am
by answerhappygod
1.
a)
1 A B 1
1 A B 1 (80.31 KiB) Viewed 54 times
b)
1 A B 2
1 A B 2 (81.38 KiB) Viewed 54 times
Analyze the following project information and apply Critical Path Method to calculate earliest and latest start time, earliest and latest finish time, slack time for all the activities and find out the critical activities and critical path of the project. Activity List A B C D E F G H Duration 8 5 6 3 7 4 5 1 Dependency A B с - E C,D
Analyze the following project information and apply Critical Path Method to calculate slack time for all the activities and find out the critical activities and critical path of the project. Activity List A B с D E F G H Duration 6 4 3 4 3 10 3 2 Dependency A B B E C,D