Problem 3 The lost time due to starting delays and end of green time on a traffic signal approach = 2 seconds. Given tha
Posted: Mon Jul 11, 2022 10:11 am
Problem 3 The lost time due to starting delays and end of green time on a traffic signal approach = 2 seconds. Given that the actual green time is 25 seconds and amber time 3 seconds. a) Find the effective green time for the given phase. b) Assuming the intersection has 4 phases, what will be the total lost time per cycle? If each phase has the same lost time