Still based on the following diagram, apply the critical path method (CPM). The number in each box refers to the duratio

Posted: Mon Jul 11, 2022 10:08 am
by answerhappygod
Still based on the following diagram, apply the critical pathmethod (CPM). The number in each box refers to the duration of thistask. Which of the following task is NOT on thecritical path?
Still Based On The Following Diagram Apply The Critical Path Method Cpm The Number In Each Box Refers To The Duratio 1
Still Based On The Following Diagram Apply The Critical Path Method Cpm The Number In Each Box Refers To The Duratio 1 (24.66 KiB) Viewed 27 times
Note i need solution for this above question (answer thequestion as soon as possible)
Note : Use below textbook.
Notes: Construction Management, 5th Edition
This is the primary textbook
Project Management in the Oil and Gas Industry
A ND 2 B 3 с 4 D 5 2 2 E3 F 1 G 2 3 H 4 2 K NX 2