Based on the following diagram, apply the critical path method (CPM). The number in each box refers to the duration of t
Posted: Mon Jul 11, 2022 10:08 am
Notes: Construction Management, 5th Edition
This is the primary textbook
Project Management in the Oil and Gas Industry
Based on the following diagram, apply the critical path method (CPM). The number in each box refers to the duration of this task. Which of the following is the total duration of this project? (A) 15 B 14 C) 13 16 A 2 33 B 3 D 5 2 2 E3 3 G 2 3 H 4 2 K 2