ABC company needs 50,000 U /year , each order costs the company 180 $ , while each unit costs 3 $ to be hold . Now , the
Posted: Mon Apr 25, 2022 7:29 am
ABC company needs 50,000 U /year , each order costs the company
180 $ , while each unit costs 3 $ to be hold . Now , the company
used to place two orders /year , but they think to change this
policy to one of the following options : A: applying the EOQ B:
establishing a production line with a capacity of 350 U/ day
Conduct a total comparison between the three options and recommend
one of them .
180 $ , while each unit costs 3 $ to be hold . Now , the company
used to place two orders /year , but they think to change this
policy to one of the following options : A: applying the EOQ B:
establishing a production line with a capacity of 350 U/ day
Conduct a total comparison between the three options and recommend
one of them .