QUESTION 22 Electrify Appliances Inc. wants to determine the optimal production policy for their best selling microwave.
Posted: Sun Jul 10, 2022 10:17 am
QUESTION 22 Electrify Appliances Inc. wants to determine the optimal production policy for their best selling microwave. The demand for this em has been relatively constant at about 12.000 each year The production capacity for this product is limited to 200 units per day. Each time production starts, it costs the company 500 to move materials into place, reset the assembly ine, and dea the equipment. The holding cost of a microwave is $10 per unit per year. Assume there are 200 working days per year. If Electrify Ino wants to minimize the total anual evertory cost tow many microwaves should be produced in each production run? 1005.06 213.81 O 1.000 O 345.65 Ⓒ3,200
QUESTION 24 The annual demand of a certain item is 1000 units and the computed EOQ is 200 units. How many orders do they have to place per year? (enter your answer in the box below) 4
QUESTION 26 Given an activity's optimistic, most likely, and pessimistic time estimates of 2, 8, and 20 days respectively, compute the PERT expected activity time for this activity 02 08 09 10 O 20
QUESTION 28 The following four activities were identified as being on the orical path of a large project. The project manager widt crashed first? Activity <HCOCO000 A OA OB Normal Time (weeks) 12 8 D 11 Normal Cost $15,000 $17,500 $12,200 $12,780 Crash Time (weeks) 8 OC OD O cannot tell from the information given 7 7 Crash Cost $18,000 518,050 $14,750 $14,500 the completion time Which y sut be
QUESTION 24 The annual demand of a certain item is 1000 units and the computed EOQ is 200 units. How many orders do they have to place per year? (enter your answer in the box below) 4
QUESTION 26 Given an activity's optimistic, most likely, and pessimistic time estimates of 2, 8, and 20 days respectively, compute the PERT expected activity time for this activity 02 08 09 10 O 20
QUESTION 28 The following four activities were identified as being on the orical path of a large project. The project manager widt crashed first? Activity <HCOCO000 A OA OB Normal Time (weeks) 12 8 D 11 Normal Cost $15,000 $17,500 $12,200 $12,780 Crash Time (weeks) 8 OC OD O cannot tell from the information given 7 7 Crash Cost $18,000 518,050 $14,750 $14,500 the completion time Which y sut be