Calculate the Present Value (to 2 d.p.) of a system overhaul that costs $18545 and occurs in Year 6 of operation of a pr

Posted: Mon Apr 18, 2022 9:49 am
by answerhappygod
Calculate The Present Value To 2 D P Of A System Overhaul That Costs 18545 And Occurs In Year 6 Of Operation Of A Pr 1
Calculate The Present Value To 2 D P Of A System Overhaul That Costs 18545 And Occurs In Year 6 Of Operation Of A Pr 1 (9.71 KiB) Viewed 21 times
Calculate the Present Value (to 2 d.p.) of a system overhaul that costs $18545 and occurs in Year 6 of operation of a project that has a discount rate of 9% and an inflation rate of 3%. Answer: