8. Perform quantity take off & cost estimate of the following foundation as per the sketch shown below. Additional infor
Posted: Fri Jul 08, 2022 5:51 am
by answerhappygod

- 8 Perform Quantity Take Off Cost Estimate Of The Following Foundation As Per The Sketch Shown Below Additional Infor 1 (23.42 KiB) Viewed 38 times

- 8 Perform Quantity Take Off Cost Estimate Of The Following Foundation As Per The Sketch Shown Below Additional Infor 2 (23.56 KiB) Viewed 38 times
8. Perform quantity take off & cost estimate of the following foundation as per the sketch shown below. Additional information for estimating cost & quantities are provided below: a. The footing is 3 ftX3 ft and 1ft 3 inches deep b. Pedestal is 1 ftX1 ft and 12 ft deep c. Total depth of foundation (footing & pedestal) is 13 ft 3 inches below ground level d. Cost of digging is = $25/CY ( includes labor and equipment cost) e. Cost of concrete is $125/CY f. Cost of rebar is:# 4 bar =$0.5/LF; #5 bar $0.75/LF Forms work timber cost $5/LF 8. Please use XL- table for calculations preferably. And use a correct format of the chart as per the estimating codes. upl bow
#5 DOWELS 12" O.C. ALTERNATING DIRECTIONS #4 REBAR @ 12" O.C. 5 EACH #4 CONT, REBAR 13" 13