Page 1 of 1

1. Cost information from five previously completed apartments building projects is given in the following table. Project

Posted: Fri Jul 08, 2022 5:50 am
by answerhappygod
1 Cost Information From Five Previously Completed Apartments Building Projects Is Given In The Following Table Project 1
1 Cost Information From Five Previously Completed Apartments Building Projects Is Given In The Following Table Project 1 (31.64 KiB) Viewed 52 times
1. Cost information from five previously completed apartments building projects is given in the following table. Project Total Cost ($) No. Apartments 1 $ 5,540,000 30 2 $10,620,000 95 $ 7,844,000 100 $ 5,782,000 55 $ 13,496,000 78 3. 4 5 a) Calculate the weighted unit cost. b) What is the estimated cost for a project with 86 apartments c) Using the graphical method, find the unit cost equation and estimate the cost for 86 apartments building.