1. Cost information from five previously completed apartments building projects is given in the following table. Project

Posted: Fri Jul 08, 2022 5:49 am
by answerhappygod
1 Cost Information From Five Previously Completed Apartments Building Projects Is Given In The Following Table Project 1
1 Cost Information From Five Previously Completed Apartments Building Projects Is Given In The Following Table Project 1 (28.93 KiB) Viewed 52 times
1. Cost information from five previously completed apartments building projects is given in the following table. Project Total Cost (S) No. Apartments 1 $ 5,540,000 2 $ 10,620,000 3 $ 7,844,000 $ 5,782,000 $ 13,496,000 4 5 30 95 100 55 78 a) Calculate the weighted unit cost. b) What is the estimated cost for a project with 86 apartments c) Using the graphical method, find the unit cost equation and estimate the cost for 86 apartments building.