d) When there is res 15. Assuming that each activity needs the same type of resource, for the project whose information
Posted: Thu Jul 07, 2022 2:23 pm
d) When there is res 15. Assuming that each activity needs the same type of resource, for the project whose information is given in the table; a) What is the resource requirement in the third day? (8p) b) What is the resource requirement in the third day after making the necessary resource smoothing? (8p) Activity Predecessors ABCDEFG === A A A B, C B, D E, F Duration, day 2 5 3 2 3 2 Labour number 2 3 3 4 2 3 3