3. [5/20 Points] PREVIOUS ANSWERS ASWMSCI15 9.E.016. ASK YOUR TEACHER PRACTICE ANOTHER Management Decision Systems (MDS)
Posted: Wed Jul 06, 2022 12:24 pm
company that specializes in the development of decision support systems. MDS has a four-person team working on a current project with a smal company to set up a system that scrapes data from a collection of websites and then automatically generates a report for management on a daily basis. Time (Weeks) Immediate Predecessor Optimistic Most Probable Pessimistic DETAILS Activity A Report generation Web scraping Testing (4) Construct the project network, (Submit a file with a maximum size of 1 MB) Choose File No fle chosen Description B C This answer has not been graded yet. A, B 2 5 1 . 1 12 4 (d) Should you use the estimate in (b) or (c) O The probability estimate from () based on the critical path is more accurate The probability estimate from (c) based on both paths is more accurate The probability estimates from (b) and (c) are equal MY NOTES (b) Besed solely on the critical path, estimate the probability that the project will be complete within 11 weeks. (You may need to use the appropriate technology to answer this question, Round your answer to four decimal places) (c) Using all paths through the project network, estimate the probability that the project will be complete within 11 weeks. (You may need to use the appropriate technology to answer this question Round your answer to four decimal places)
3. [5/20 Points] PREVIOUS ANSWERS ASWMSCI15 9.E.016. ASK YOUR TEACHER PRACTICE ANOTHER Management Decision Systems (MDS) is a consulting