Activity P on a project has exactly 4 predecessors A, B, C, and D whose ear days are 20, 12, 38, and 32. (Here "day" mea
Posted: Wed Jul 06, 2022 12:04 pm
Activity P on a project has exactly 4 predecessors A, B, C, and D whose ear days are 20, 12, 38, and 32. (Here "day" means days after project start.) W early start day of P? 13 38 039 21