The demand for product S is 150 units at the beginning of week 6. Each product S needs 2 T units and 3 U units. Eac
Posted: Wed Jul 06, 2022 6:15 am
The demand for product S is 150 units at the beginning of week6. Each product S needs 2 T units and 3 U units. Each Tunit needs 2 V units, 1 W unit, and 4 X units. Each U unitneeds 3 Y units and one X unit. One company manufactures all the items. The lead time for Sis one week, T is 2 weeks, U is 2 weeks, V is 2 weeks, W is 3weeks, X is one week, and Y is 2 weeks.
d) In addition to 150 units of S at the beginning of week 6,there is a request for 50 units of U, which is a component of S.The 50 units are required for maintenance purposes. These 50units are due to be delivered at the beginning of week 4. Reviseyour PBM/MRP to reflect this change. e) Is there a feasible solution in part d)? Justify your answer. Ifthere is no feasible solution, give a recommendation on how it canbe made feasible.
d) In addition to 150 units of S at the beginning of week 6,there is a request for 50 units of U, which is a component of S.The 50 units are required for maintenance purposes. These 50units are due to be delivered at the beginning of week 4. Reviseyour PBM/MRP to reflect this change. e) Is there a feasible solution in part d)? Justify your answer. Ifthere is no feasible solution, give a recommendation on how it canbe made feasible.