An initial time study was done on a process with the following results (in minutes). Based on the data obtained so far,

Posted: Wed Jul 06, 2022 6:15 am
by answerhappygod
An Initial Time Study Was Done On A Process With The Following Results In Minutes Based On The Data Obtained So Far 1
An Initial Time Study Was Done On A Process With The Following Results In Minutes Based On The Data Obtained So Far 1 (195.44 KiB) Viewed 12 times
An initial time study was done on a process with the following results (in minutes). Based on the data obtained so far, assuming an allowance of 13 percent of the normal time, what do you estimate for the time per customer served, based on this preliminary sample? (Round all intermediate calculations to two decimal places.) The time per unit customer served is Element Element 1 Element 2 Element 3 Performance Rating 110 130 80 Obs 1 4 11 6 Obs 2 3 10 7 Obs 3 3 11 6 minutes. (Enter your response rounded to two decimal places.) Obs 4 3 10 6 Obs 5 6 9 7