Russo Corporation manufactured 17,000 air conditioners during November. The overhead cost-allocation rate is $35.50 per
Posted: Wed Jul 06, 2022 6:12 am
Russo Corporation manufactured 17,000 air conditioners during November. The overhead cost-allocation rate is $35.50 per machine-hour. The following variable overhead data pertain to November Production Machine-hours Variable overhead cost per machine-hour What is the variable overhead efficiency variance? OA. $6,212,50 unfavorable B. $6,212.50 favorable C. $4,750.00 favorable OD. $4,750.00 unfavorable Actual 17,000 units 8,325 hours $35.00 Budgeted 19,000 units 9,500 hours $35.50