Consider the following four--‐step assembly operation with quality problems. -The first resource has a processing time o
Posted: Wed Jul 06, 2022 6:07 am
Consider the following four--‐step assembly operation withquality problems.
-The first resource has a processing time of 5 minutes per unitand one employee doing the operation
‐ The second resource has a processing time of 4 minutes perunit. It also has one employee doing the operation. However, thisis a very delicate task and 0.80 of all products have to bescrapped after this step.
‐ Two workers are staffed for the third resource. No qualityproblems occur at this resource and the processing time is23minutes per unit. ‐ At the fourth and final resource, oneoperator handles the product. No quality problems exist at thisstep and the processing time is 12 minutes per unit.
What is the process capacity per hour? (keep two decimal)
-The first resource has a processing time of 5 minutes per unitand one employee doing the operation
‐ The second resource has a processing time of 4 minutes perunit. It also has one employee doing the operation. However, thisis a very delicate task and 0.80 of all products have to bescrapped after this step.
‐ Two workers are staffed for the third resource. No qualityproblems occur at this resource and the processing time is23minutes per unit. ‐ At the fourth and final resource, oneoperator handles the product. No quality problems exist at thisstep and the processing time is 12 minutes per unit.
What is the process capacity per hour? (keep two decimal)