b) Mikio Cast Sdn. Bhd. Sets up an assembly line to produce 192 units per 8-hour shift. Table 2 identifies the work elem

Posted: Wed Jul 06, 2022 6:07 am
by answerhappygod
B Mikio Cast Sdn Bhd Sets Up An Assembly Line To Produce 192 Units Per 8 Hour Shift Table 2 Identifies The Work Elem 1
B Mikio Cast Sdn Bhd Sets Up An Assembly Line To Produce 192 Units Per 8 Hour Shift Table 2 Identifies The Work Elem 1 (105.01 KiB) Viewed 14 times
b) Mikio Cast Sdn. Bhd. Sets up an assembly line to produce 192 units per 8-hour shift. Table 2 identifies the work elements, times, and predecessors. i) Determine the desired cycle time (in seconds). ii) What is the theoretical minimum number of stations? iii) Use trial and error to work out a solution, and show your solution on a precedence diagram. Work Element A B C Table 2: Data for Production Line Time (sec) D E 40 80 30 25 [2 marks] [CO4, PO4, C5] 20 [2 marks] [CO4, PO4, C5] [6 Marks] [CO4, PO4, C5] Predecessor(s) None A D, E, F B B