The budget at completion for your project is $200,000. Your project's earned value is $125,000, while actual cost is $15
Posted: Wed Jul 06, 2022 6:06 am
The budget at completion for your project is $200,000. Yourproject's earned value is $125,000, while actual cost is $150,000.For the remainder of the project, you expect the same CPI. What isthe estimate at completion?
Group of answer choices
a. $220,000
b. $240,000
c. $210,000
d. $250,000
Group of answer choices
a. $220,000
b. $240,000
c. $210,000
d. $250,000